A network administrator installs new cabling to connect new computers and access points. After deploying the equipment, the administrator notices a few of the devices are not connecting properly. The administrator moves the devices to a different port, but it does not resolve the issue. Which of the following should the administrator verify next?


A.

Power budget


B.

Device requirements


C.

Port status


D.

Cable termination