CompTIA Project+ PK0-005 Question # 2 Topic 1 Discussion

PK0-005 Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?


A.

Evaluating the project


B.

Releasing the resources


C.

Closing the contracts


D.

Reconciling the budget