CompTIA Project+ PK0-005 Question # 3 Topic 1 Discussion

PK0-005 Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?


A.

The retrospective session feedback was not communicated properly.


B.

The project resources were released ahead of time.


C.

The documentation was not archived as per the PMO standards.


D.

The validation of deliverables is running behind schedule.