Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PK0-005 All Questions
Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

CompTIA Project+ PK0-005 Question # 91 Topic 10 Discussion

PK0-005 Exam Topic 10 Question 91 Discussion:
Question #: 91
Topic #: 10

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?


A.

Update the WBS.


B.

Escalate to the CCB.


C.

Accept the change.


D.

Implement the change.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.