Which of the following activities should a project manager perform during the closing phase? (Select three).


A.

Lessons learned


B.

Risk analysis


C.

Removing resources


D.

Acquiring resources


E.

Statement of work sign-off


F.

Stakeholder analysis


G.

Removing access