CompTIA Project+ PK0-005 Question # 115 Topic 12 Discussion

PK0-005 Exam Topic 12 Question 115 Discussion:
Question #: 115
Topic #: 12

During an active project, the finished product is not meeting quality specifications Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?


A.

Communicate the change status.


B.

Document change recommendations


C.

Create a change request.


D.

Implement the changes