Question #: 118
Topic #: 12

During the testing phase of a project, an executive raises a concern about a missing requirement in the product. Which of the following is the next step the project manager should take?


A.

Communicate the change status.


B.

Ask for a change request submission


C.

Escalate to the change control board


D.

Reject the change to prevent scope creep.