Question #: 123
Topic #: 13

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?


A.

Performing


B.

Adjourning


C.

Forming


D.

Norming