Spring Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PK0-005 All Questions
Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

CompTIA Project+ PK0-005 Question # 197 Topic 20 Discussion

PK0-005 Exam Topic 20 Question 197 Discussion:
Question #: 197
Topic #: 20

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?


A.

Status report


B.

Issue log


C.

Risk report


D.

Risk register


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.