CompTIA Project+ PK0-005 Question # 224 Topic 23 Discussion

PK0-005 Exam Topic 23 Question 224 Discussion:
Question #: 224
Topic #: 23

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?


A.

Update the work breakdown structure.


B.

Review the backlog.


C.

Seek baseline approval.


D.

Establish the resource pool.