CompTIA Project+ PK0-005 Question # 17 Topic 3 Discussion

PK0-005 Exam Topic 3 Question 17 Discussion:
Question #: 17
Topic #: 3

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?


A.

Status report


B.

Issue log


C.

Risk report


D.

Risk register