CompTIA Project+ PK0-005 Question # 24 Topic 3 Discussion

PK0-005 Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?


A.

Communicate with the affected stakeholders.


B.

Initiate a formal change request to modify the cost


C.

Adjust the scope to stay within the cost.


D.

Set a new cost using a lightweight estimation method.