CompTIA Project+ PK0-005 Question # 44 Topic 5 Discussion

PK0-005 Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?


A.

Time to be fixed


B.

Impact to project


C.

Issue category


D.

Resource availability