CompTIA Project+ PK0-005 Question # 46 Topic 6 Discussion

PK0-005 Exam Topic 6 Question 46 Discussion:
Question #: 46
Topic #: 6

Which of the following tasks should the project manager complete first when validating deliverables?


A.

Assess the documentation.


B.

Obtain stakeholder feedback.


C.

Review the project objectives.


D.

Mitigate risks.