Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?
A risk log or risk register is used to document potential risks to the project, including the loss of team members due to high stress. CompTIA Project+ recommends this log as a tool for identifying and managing risks throughout the project lifecycle.