CompTIA Project+ PK0-005 Question # 49 Topic 6 Discussion

PK0-005 Exam Topic 6 Question 49 Discussion:
Question #: 49
Topic #: 6

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?


A.

Obtain details from the owner of the project.


B.

Update the critical path for the project.


C.

Apply contingency reserves.


D.

Reestimate epic user stories.