CompTIA Project+ PK0-005 Question # 59 Topic 7 Discussion

PK0-005 Exam Topic 7 Question 59 Discussion:
Question #: 59
Topic #: 7

During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?


A.

Issue log


B.

Defect log


C.

Risk register


D.

Change log