Month End Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PK0-005 All Questions
Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

CompTIA Project+ PK0-005 Question # 67 Topic 7 Discussion

PK0-005 Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?


A.

Finish-to-start


B.

Start-to-start


C.

Finish-to-finish


D.

Start-to-finish


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.