CompTIA Project+ PK0-005 Question # 68 Topic 8 Discussion

PK0-005 Exam Topic 8 Question 68 Discussion:
Question #: 68
Topic #: 8

A software development team completed the development and testing of a new accounting software system for a client. Which of the following should the team do next?


A.

User acceptance testing


B.

Unit testing


C.

Performance testing


D.

Audits and inspections