CompTIA Project+ PK0-005 Question # 75 Topic 8 Discussion

PK0-005 Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?


A.

Project status report


B.

Requirements Traceability Matrix


C.

Detect log


D.

Signed project charter


E.

Work breakdown structure