A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?


A.

Validate against the scope statement and ask for sign-off.


B.

Run a control chart to ensure the quality of the deliverables.


C.

Review the risk register and close up residual risks.


D.

Start the training and handoff for the operations team.