Comprehensive and Detailed Explanation:
Option C is not true because under the FIDIC Silver Book (1999 edition), the delay damages (liquidated damages) specified in the contract are intended as full compensation for the Employer’s loss resulting from late completion. The contract usually excludes other claims for actual losses or extra costs beyond the delay damages.
Option A is true; Variations can include extensions of time.
Option B is true; identifying delay causes is essential for claims and defences.
Option D is true; if the Employer causes suspension not attributable to the Contractor, delay damages claims by the Employer are generally unjustified.
Thus, the Employer cannot claim extra costs over and above delay damages as per typical Silver Book provisions.
[References:, , FIDIC Silver Book 1999 Edition, Sub-Clause 8 – Time for Completion and Delay Damages, , FIDIC Silver Book 1999 Edition, Sub-Clause 2.5 – Employer’s Claims, , FIDIC Contract Manager Study Guide, Module on Claims and Delay Damages, ]
Submit