FIDIC Contract Manager CCM Question # 22 Topic 3 Discussion

CCM Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.


A.

True


B.

False