FIDIC Contract Manager CCM Question # 25 Topic 3 Discussion

CCM Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

Giving "Notice" .... [2017 edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).


A.

... is not a compulsory obligation, but "highly recommended".


B.

... is always compulsory together with a clear indication of the relevant Sub-Clause under which the Notice is being served.


C.

... is a special obligation for the Engineer only, in order to enable him/her to manage the implementation of the contract.


D.

... is intended for written communications, in full compliance with the formal requirements outlined in the dedicated Sub-Clause.