FIDIC Contract Manager CCM Question # 44 Topic 5 Discussion

CCM Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?


A.

True


B.

False