Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).


A.

FIDIC Conditions of Contract for Construction ("Red Book").


B.

FIDIC Conditions of Contract for Plant and Design Build ("Yellow Book").


C.

FIDIC Conditions of Contract for EPC/Turnkey Projects ("Silver Book").