As the Sprint Planning meeting progresses, the Developers see that the workload is greater than they can handle. Which two are valid actions? (Choose the best two answers)
A.
The Developers work overtime during this Sprint.
B.
Recruit additional Developers before the work can begin.
C.
Cancel the Sprint.
D.
Remove or change selected Product Backlog items.
E.
The Developers ensure that the Product Owner is aware, start the Sprint, and monitor progress.
TheScrum Guideallows the Sprint Backlog to be adjusted during Sprint Planning if the Developers realize the scope exceeds capacity: "If the work turns out to be different than they expected, they collaborate with the Product Owner to negotiate the scope of the Sprint Backlog within the Sprint."
D:Removing or changing items is valid to align with capacity while preserving the Sprint Goal.