Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PPM-001 All Questions
Exam PPM-001 All Questions

View all questions & answers for the PPM-001 exam

GAQM: Project Management PPM-001 Question # 53 Topic 6 Discussion

PPM-001 Exam Topic 6 Question 53 Discussion:
Question #: 53
Topic #: 6

The standard formula for estimating time that a task will take is…


A.

Optimistic Time + (4 x Probable Time) + Pessimistic Time, divided by 6


B.

Average of past tasks


C.

It depends on the task types


D.

middle value of the given numbers


Get Premium PPM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.