GIAC GCPM Question # 3 Topic 1 Discussion

GCPM Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

Which of the following documents is described in the statement below?

"It is a companion document to the WBS. It describes each component in the WBS. It includes a brief definition of the scope or statement of work, defined deliverables, a list of associated activities, and a list of milestones. It details all work packages in WBS including estimates and billing information."


A.

WBS dictionary


B.

Contract


C.

Project charter


D.

Activity list