Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam GCPM All Questions
Exam GCPM All Questions

View all questions & answers for the GCPM exam

GIAC GCPM Question # 12 Topic 2 Discussion

GCPM Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

You work as a project manager for PassGuide Inc. You do not want to change the task relationship, but you require a "waiting time" before the starting of the activity can begin. Which of the following is the best approach to alleviate this issue?


A.

Add management reserve to the project activities.


B.

Add lag time to the project activities.


C.

Add lead time to the project activities.


D.

Add float to the project activities.


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.