You work as a Project Manager for PassGuide Inc. You are developing the schedule for your project. Your project deals with the construction of a new building for PassGuide Inc. You want to break the project into small, individual, and manageable components. Which of the following tasks will you perform in the above scenario?


A.

Create WBS.


B.

Create a Gantt chart.


C.

Create an activity diagram.


D.

Create a PERT chart.