GIAC GCPM Question # 20 Topic 3 Discussion

GCPM Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3

Jessica works as a project manager for PassGuide Inc. She wants to discuss with the team members some of the project risks and issues that have occurred. Jessica has faxed the report to her project team for them to review. Based on the standard communications model, which component in this scenario is the decoder?


A.

Fax machine


B.

Team member


C.

Jessica


D.

Telephone wire