GIAC GCPM Question # 22 Topic 3 Discussion

GCPM Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?


A.

Project change control process


B.

Configuration management


C.

Perform integrated change control process


D.

Communications management


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer: