Dawn is the project manager of the HQQ Project and she believes the project work is done. She has prepared the final project report, which includes information on the financial performance, schedule performance, and project team performance in the project. All of the following documents are used to measure the completeness of the project scope except for which one?


A.

Project scope statement


B.

Project charter


C.

Project WBS Dictionary


D.

Project WBS