Question #: 32
Topic #: 4

You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You know that developers are available in your organization, and would like to use them. However, your program manager thinks that an outside company needs to be engaged to complete this development. Which of the following will help you to convince your project manager to use the internal resources?


A.

Expert Judgment


B.

Make or buy analysis


C.

Survey Questionnaire


D.

Issue log