Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam GCPM All Questions
Exam GCPM All Questions

View all questions & answers for the GCPM exam

GIAC GCPM Question # 36 Topic 4 Discussion

GCPM Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

You work as a project manager for PassGuide Inc. You are performing a task to generate a hierarchical list of resources related by function and resource type that is used to facilitate planning and controlling of project work. Which of the following components of project management will you use to accomplish the above task?


A.

PERT chart


B.

WBS


C.

RBS


D.

Gantt chart


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.