GIAC GCPM Question # 38 Topic 4 Discussion

GCPM Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

Which of the following techniques is described in the statement below?

"It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid of any resource limitations by performing a forward and backward pass analysis through the schedule network."


A.

Resource utilization


B.

Resource leveling heuristic


C.

Critical path method


D.

Critical Chain method