You work as a project manager for PassGuide Inc. Your project has a schedule variance of -$35,500 and a schedule performance index of 0.92. What do these values mean in regard to project performance?
A.
The project is performing well.
B.
The project has a planned value of $600,000.
C.
The project is likely to be late and over budget.
D.
The project is eight percent off schedule and has a considerable schedule variance.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.