Question #: 39
Topic #: 4

You work as a project manager for PassGuide Inc. Your project has a schedule variance of -$35,500 and a schedule performance index of 0.92. What do these values mean in regard to project performance?


A.

The project is performing well.


B.

The project has a planned value of $600,000.


C.

The project is likely to be late and over budget.


D.

The project is eight percent off schedule and has a considerable schedule variance.