GIAC GCPM Question # 41 Topic 5 Discussion

GCPM Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

Which of the following are the tasks performed by the Work breakdown structure (WBS)?

Each correct answer represents a complete solution. Choose all that apply.


A.

It separates the major project deliverables into smaller components to improve the accuracy of cost estimates.


B.

It defines assignable resources, such as personnel, from a functional point of view.


C.

It provides a mechanism for collecting and organizing actual costs.


D.

It provides a mechanism for performance measurement and control.