GIAC GCPM Question # 57 Topic 6 Discussion

GCPM Exam Topic 6 Question 57 Discussion:
Question #: 57
Topic #: 6

Alan works as a project manager for PassGuide Inc. He is working on the office renovation project. The office has 200 doors. All doors have to be glassed and painted. Before each door can be painted, the glasses must be fitted in them at least 12 hours before. Alan has arranged these tasks with a finish to start relationship between glassing and painting. What else should Alan do to account for the twelve hours of maintenance time?


A.

Alan must add twelve hours of lead time to each of the 200 doors painting activity to account for the glassed maintenance time.


B.

Alan must schedule all 200 office doors to be glassed first and then schedule all 200 doors to be painted to ensure time for the maintenance.


C.

Alan must add twelve hours of lag time to each of the 200 doors painting activity to account for the glassed maintenance time.


D.

Alan must add an intermediary task with duration of twelve hours.