Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam GCPM All Questions
Exam GCPM All Questions

View all questions & answers for the GCPM exam

GIAC GCPM Question # 77 Topic 8 Discussion

GCPM Exam Topic 8 Question 77 Discussion:
Question #: 77
Topic #: 8

You work as a project manager for PassGuide Inc. You have to evaluate the performance efficiencies of a project. The table given below has the following related values:

GCPM Question 77

Which of the following will be the cost variance (CV) of the project at the current point of time?


A.

-25


B.

30


C.

25


D.

-30


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.