GIAC GCPM Question # 78 Topic 8 Discussion

GCPM Exam Topic 8 Question 78 Discussion:
Question #: 78
Topic #: 8

You work as a project manager for PassGuide Inc. You want to standardize your department's personnel resources to facilitate planning and controlling of project work. Which of the following components of project management will help you accomplish the task?


A.

Gantt chart


B.

Project network diagram


C.

RBS


D.

WBS