Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam GCPM All Questions
Exam GCPM All Questions

View all questions & answers for the GCPM exam

GIAC GCPM Question # 83 Topic 9 Discussion

GCPM Exam Topic 9 Question 83 Discussion:
Question #: 83
Topic #: 9

You work as a project manager for PassGuide Inc. Your project was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is an additional hour. The project should have been completed already. An hourly rate of $100 per hour is provided, and the project is 91.7% complete.

Which of the following is the correct CPI for the project?


A.

0.86


B.

0.67


C.

0.45


D.

0.53


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.