Which of the following are the prime reasons behind the use of the Critical path method in a project?
Each correct answer represents a complete solution. Choose all that apply.
It categorizes the tasks that can be delayed for a while if resources need to be reallocated to catch up on missed tasks.
It determines both the early start and the late start date for each activity in the schedule.
It identifies the tasks that should be completed on time for the whole project to be completed on time.
It is used to describe the maximum length of time needed to complete a project.