Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Exam GCPM All Questions
Exam GCPM All Questions

View all questions & answers for the GCPM exam

GIAC Certified Project Manager Certification Practice Test GCPM Question # 85 Topic 9 Discussion

GCPM Exam Topic 9 Question 85 Discussion:
Question #: 85
Topic #: 9

Which of the following are the prime reasons behind the use of the Critical path method in a project?

Each correct answer represents a complete solution. Choose all that apply.


A.

It categorizes the tasks that can be delayed for a while if resources need to be reallocated to catch up on missed tasks.


B.

It determines both the early start and the late start date for each activity in the schedule.


C.

It identifies the tasks that should be completed on time for the whole project to be completed on time.


D.

It is used to describe the maximum length of time needed to complete a project.


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.