GIAC Management GSLC Question # 11 Topic 2 Discussion

GSLC Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

You and your project team have identified the project risks and now are analyzing the probability and impact of the risks. What type of analysis of the risks provides a quick and high-level review of each identified risk event?


A.

Quantitative risk analysis


B.

Seven risk responses


C.

Qualitative risk analysis


D.

A risk probability-impact matrix