You are installing a rack at customer site.

How can you ensure redundant power to the rack?


A.

Install two power distribution units (PDUs) with each one connected to a power socket supplied by an independent electrical power source.


B.

Ensure 3-phase power is available in the data center.


C.

Connect an uninterruptible power supply (UPS) to redundant circuit breakers at the facility power source.


D.

Use two different power cords to connect the server to the power grid at the customer site.