Question #: 14
Topic #: 2

An architect proposes an Aruba solution with a hardware Mobility Master (MM) to a customer. The customer has a disaster recovery site which is connected to the main site at Layer 3. The customer requires the MM to remain available in case of a total site failure.

Which plan meets the customer requirements?


A.

Deploy a hardware MM to the disaster recovery site and set up VRRP between them.


B.

Deploy a hardware MM to the disaster recovery site and set its IP address as the standby master for MCs.


C.

Deploy the virtual MM (VMM) to the disaster recovery site and set the VMM IP address to the same address as the hardware MM.


D.

Deploy the virtual MM (VMM) to the disaster recovery site and configure clustering on the hardware and software appliances.