Huawei HCIP-Storage H13-624 Question # 195 Topic 20 Discussion

H13-624 Exam Topic 20 Question 195 Discussion:
Question #: 195
Topic #: 20

In the Oceanstor 9000 system, if a node is offline for 2 days due to a power module failure, it returns to normal again.

If the administrator does not manually restore the data of the node, the system will automatically update the data that has changed during the offline period to this node.

Restore the normal node.


A.

True


B.

False