IIA CIA IIA-CIA-Part1 Question # 99 Topic 12 Discussion

IIA-CIA-Part1 Exam Topic 12 Question 99 Discussion:
Question #: 99
Topic #: 12

Which of the following is true regarding risk analysis?


A.

Impact and likelihood should be assessed together.


B.

Impact and likelihood should be given equal consideration by the internal auditor.


C.

Impact and likelihood should be measured using quantitative methods.


D.

Impact and likelihood should be used to determine risk response.