An organization that takes no action in managing the possible exposure to an earthquake is adopting an acceptance technique in terms of its risk response. This technique involves acknowledging the risk but choosing not to take any proactive steps to manage it, essentially accepting the potential consequences.
Risk management strategies as per IIA guidance.